Client: Deutsche Einheit Fernstraßenplanungs- und ‑bau GmbH (DEGES)
Object: A44 | new section BA5 | TU Alberberg | Unhausen
Period: 2021 to 2024
The A44 is part of the German Unity Transport Project No. 15: “Autobahn A44 Kassel — Eisenach and A4 Eisenach — Görlitz” and is intended to close a gap in the federal highway network on the Ruhr area — Kassel — Dresden axis between the A7 near Kassel and the A4 near Wommen. The commissioned construction section BA5 has a total length of approx. 9 km east of the town of Sontra and connects to the A4 at the village of Wommen. The contract is being executed in a joint venture. The following structures will be built by AUGUST REINERS Bauunternehmung GmbH:
- Construction of the Alberberg Tunnel (BW C24/07T), 2 tubes in closed, semi-open and open construction method
- Construction of the “retaining wall — B 400” structure (BW C24/07.1 STW) at the connection to the Alberberg tunnel
- Construction of the structure “Retaining wall — along exit ramp RFB Herleshausen” (BW C24/03.3 STW)
- Construction of the “Forstweg underpass in Gerbachsgrund” structure (BW C24/04A)
- Construction of the “bat passage” structure (BW C24/15A)
- Construction of the “Blankebach KVP B 400 underpass” structure (BW C24/37)
- Construction of the “retaining wall — Lengforst” structure (BW C24/13 STW)
- Construction of operations building, extinguishing water basin and pollutant retention basin
- Construction of embankment protection for tunnel pre-cuts, retaining wall — B 400 (BW C24/07.1 STW), retaining wall — Lengforst (BW C24/13 STW) and retaining wall — along exit ramp RFB Herleshausen (BW C24/03.3 STW).
TECHNICAL DATA
Tunnel length: 1x 508 m (BBW 358 m, HOBW 130 m, OBW 20 m) | 1x 427 m (BBW 300 m, HOBW 107 m, OBW 20 m)
Excavated volume: approx. 72,000 m³ BBW | approx. 12,000 m³ HOBW
Cross-section: approx. 100 m²
Installed quantity of concrete: approx. 17,700 m³ tunnel | approx. 11,600 m³ civil engineering
Installed quantity of steel: approx. 3,200 tons tunnel | approx. 1,600 tons civil engineering
Installed quantity of shotcrete: approx. 13,600 m³ tunnel | approx. 2,940 m³ slope stabilization